- Home
- Press Room
- Largest Road Project in Tulsa’s History Nearly Complete: South Yale Avenue, 81st – 91st Street Set to Open Next Week
Largest Road Project in Tulsa’s History Nearly Complete: South Yale Avenue, 81st – 91st Street Set to Open Next Week
8/13/2024
This article was archived on 9/3/2024
The project to widen South Yale Avenue between East 81st Street and East 91st Street from two lanes to six lanes is nearing completion after several years of construction. Mayor G.T. Bynum and District 8 City Councilor Phil Lakin will hold a celebration on Monday, August 19 as the City opens the long-awaited stretch of Yale.
Completing this project marks a historic moment for the City of Tulsa and one of the City’s busiest streets.
"At the completion of the largest road project in Tulsa's history, it's amazing to see how Yale Avenue has been transformed from a risky, curvy, two-lane road to a much safer six-lane road with sidewalks and landscaping," Mayor G.T. Bynum said. "I’m so thankful the opening is around the corner, and I want to thank the citizens of Tulsa for their support and patience through the construction of our new Yale Avenue.”
Those driving on this new mile of Yale Avenue will drive over 9-inch-thick concrete and have four additional lanes than before. The six lanes are divided in half by a raised, landscaped center median with dedicated left-turn bays. Pedestrians will now get to experience new 6-foot-wide sidewalks that have been added on both sides of the road. The total cost for the project is $31 million, which was funded by the Improve Our Tulsa sales tax. The project finished $9 million under the engineer’s original cost estimate.
"Widening roads to resolve massive traffic backups and improve safety is one of my key objectives. Yale had been #1 on the widening list for well over a decade when I took office, yet no council had allocated funding,” said District 8 Councilor Phil Lakin Jr. “I fixed this and secured millions by partnering with my fellow councilors and demonstrating the need. And Yale will never be the same: the deadly curve that claimed lives and caused countless accidents is gone; 6 lanes replace 2, and a turn lane protects drivers crossing traffic; and, beautiful landscaping and hardscaping finish out the project the right way, restoring beauty to the corridor. I’m so very proud of our collective work and deeply thank the neighbors, engineers, contractors, and public for their trust and support."
Benefits of the construction and new road include:
- Improved capacity for higher traffic volumes
- Safer turning movements
- Smooth grading between street and retaining walls to eliminate drop-offs
-
Tight curves flattened to improve sight distance
-
Additionally, the stormwater drainage system capacity has been expanded to accommodate a 1 percent chance of flooding in any given year. Pipe sizes have been increased to up to 36 inches in diameter.
A new waterline main has been installed on the east side of Yale, 16 inches in diameter and new 8-inch laterals have been installed, connecting to the neighborhood systems. A total of 13 decorative concrete retaining walls have been constructed on both sides of the street, as well as a new 85th Street entrance to the Brookwood subdivision. In the raised median that divides the six lanes, cypress, maple, pine and other trees have been planted where feasible along with other improved landscaping features.
The engineering consultant for this project was Benham, and the contractor was Becco Contractors. Planning Design Group was the landscape architect.